As redevelopment approaches possession, dozens of small unfinished items may remain across flats, common areas, services and amenities.
Advance PMC believes societies should maintain a structured pending works register before final handover, recording each issue, responsibility and rectification status.
This prevents unfinished work from being forgotten once members begin moving back and the site team starts reducing its presence.
Possession should not automatically mean closure. Advance PMC helps societies ensure that outstanding work remains visible, documented and accountable until completion.
Practical Pre-Handover Checklist
Inspect individual member flats.
Check common-area finishes.
Verify lifts and building services.
Inspect waterproofing-sensitive areas.
Check fire and safety systems.
Verify promised amenities.
Record incomplete or defective items with photographs.
Assign responsibility for each pending item.
Add target rectification dates.
Close each item only after physical verification.

Leave a Reply